How a Road or Driveway Is Spray Sealed, Step by Step, and When Traffic Can Return

A Queensland spray seal (also called chip seal, or ‘tar’) is bitumen sprayed onto a prepared base and covered at once with stone. The crew checks and sweeps the base, primes or primerseals a new base, sprays the bitumen, spreads and rolls the stone, then sweeps off loose stone. Traffic returns slowly, on the crew’s directions.

Updated 25 September 2026.

Planning a seal? Book an on-site assessment and we’ll walk you through what your job involves. Based in Cooroy, working across the Sunshine Coast, Noosa and Gympie, Brisbane north, Moreton Bay, the Fraser Coast, the Burnetts, Bundaberg, Toowoomba and the Western Downs. See our service areas.

How do I seal a bitumen driveway?

You book a spray sealing crew; it is not a DIY job. The crew checks and sweeps the base, primes or primerseals a new base, sprays the bitumen, spreads stone over it, rolls it and sweeps off the loose stone. It takes a sprayer truck, a stone spreader, a rubber-tyred roller and a road broom.

The steps are the same for a road, a yard or a long rural drive; the size of the job, truck access and, on roads, traffic control are what change. See our bitumen spray sealing service for roads and yards, or how we seal driveways on the Sunshine Coast for homes and acreage.

The steps at a glance

  1. Site check: the base’s strength, shape, drainage and surface.
  2. Sweep: loose material off, until the larger stones in the surface just show.
  3. Prime or primerseal: a first bituminous layer, on a new base only; a reseal skips it.
  4. Spray: hot bitumen or a bitumen emulsion, applied evenly at the designed rate.
  5. Spread: stone straight onto the fresh binder, one stone thick.
  6. Roll: rubber-tyred rollers press the stone in and turn it onto its flat side.
  7. Reopen and sweep: slow traffic first, then loose stone swept off once the stone has bedded in.
Step What you see on the day Your part
1. Site check A walk-around of the base, drainage, edges and access Point out soft spots, buried pipes and tight access
2. Sweep Broom passes lifting dust and loose gravel Keep cars and bins off the area
3. Prime or primerseal A dark, even coat on a new base; a prime is usually a separate visit Keep traffic to what the crew allows
4. Spray The sprayer truck at work and a bitumen (hydrocarbon) smell Keep people and pets clear; avoid breathing the fumes
5. Spread Tippers and a spreader right behind the sprayer Stay clear of reversing trucks
6. Roll Rollers making slow passes Wait for the crew’s go-ahead
7. Reopen and sweep Slow traffic, then sweeping; on TMR roads, warning signs and a lower speed limit Drive slowly and follow the crew’s instructions

Source: Austroads AGPT Part 4K (2026), sections 7.1 and 7.2; TMR MRTS11 (July 2025), clauses 10 to 14.

Driveway or road: what changes

The method is the same, but the planning differs:

  • Access: the sprayer, loaded tippers and a roller must get in, turn and get out.
  • Turning areas: turning and braking tyres pull stone from a seal, so turning circles and entrances are high-stress spots.
  • Drainage: even poorer gravel can perform satisfactorily when its moisture is well controlled.
  • Traffic control: road jobs need it; on TMR roads it falls under the MRTS02 specification.

For a private or shared road, see sealing a private or shared road.

Why a bucket driveway sealer is a different job

Driveway sealers sold in buckets are typically coatings brushed or squeegeed onto existing, weathered asphalt, rather than a new surface. A spray seal is a new surface of bitumen and stone, laid with a sprayer truck, a spreader and rollers, and on TMR work hand spraying is allowed only where the sprayer cannot reach. That is why this guide gives no do-it-yourself steps.

Before the sprayer arrives: checking and preparing the base

A spray seal is a thin waterproof surface, so it is only as good as the base under it. Before sealing day the crew checks that the base is shaped to shed water, well compacted, and dried back and firm rather than wet or soft, then sweeps it clean. Any base repairs come first.

What the site check looks at

What is checked Why it matters
Strength and compaction A seal’s performance depends on the strength and stability of the pavement under it
An even surface finish Compaction and an even finish are critical to a seal on a gravel base
Shape and drainage Even poorer gravel can perform satisfactorily when its moisture is well controlled
Moisture Austroads calls for a surface-dry base for a prime, and a slightly damp but not wet one for a primerseal
Loose material It is swept off until the larger stones just show

Source: Austroads AGPT Part 4K (2026), sections 2.3.2, 7.1.1 and 7.1.2; TMR MRTS11 (July 2025), clause 10.1.2.

What you do before the day

Your crew will tell you what it needs. Common requests are:

  • Move cars, trailers and bins off the area and well back from its edges.
  • Show the crew where irrigation lines, septic lids and buried pipes are.
  • Clear the gate and the way in for a sprayer truck and loaded tippers.
  • Tell neighbours who share the access.
  • Plan where children, pets and stock will be, well away from the work.

Who fixes the base

Soft spots, potholes and poor drainage are fixed before any bitumen goes down, because the seal relies on the base for its strength. Your quote should say who does that work.

Priming or primersealing a new base

New or reworked bases get a first bituminous layer before the final seal, either a prime or a primerseal (an ‘initial seal’ in Austroads terms). The choice depends on the base, the traffic and the timing, and your quote should say which one your job needs. Our primer seals page explains the difference and when each is used.

A reseal over an existing seal or asphalt skips this step. On new roads a primerseal can carry traffic straight away, and TMR notes that initial seals are often trafficked for several months before the final seal or asphalt. Builders and developers can read about primerseal and tack coat on estate roads.

Is the prime done on the same visit as the seal?

Usually not, if the job starts with a prime, because a prime must dry and cure first. Austroads gives a general minimum of about 3 days for a cutback prime and 1 day for an emulsion prime, and TMR jobs require at least 3 days and a completely dry prime. A primerseal carries traffic straight away; ask the crew when the final surface will follow.

Spraying the bitumen

A sprayer truck applies the binder, either hot bitumen or a bitumen emulsion, in an even film at a rate set by the seal design. Spraying also waits for the weather: on TMR jobs the specification rules it out in rain or when rain is likely, in strong wind, and on a pavement that is too cold.

In Queensland: the specification and the weather

  • Sprayed seals are the most common surface on the road network TMR manages.
  • TMR’s MRTS11 covers sprayed treatments with hot binders and MRTS12 covers emulsions; ‘primerseal’ is the MRTS12 term.
  • Emulsions gain strength more slowly than hot bitumen, so traffic may wait longer, especially in cool weather.
  • TMR’s cold-weather technical note recommends warm, dry, stable weather, because cold or damp conditions raise the risk of tyres stripping stone from a new seal.
  • At the Bureau of Meteorology’s Tewantin station near Cooroy, February and March are the wettest months on average.

Read best time of year to spray seal to plan around the seasons.

Is it tar?

No. Many people call it ‘tarring’ a road, but modern sprayed seals use bitumen refined from crude oil, and coal tar is no longer used for sprayed sealing. See bitumen vs tar for the difference.

Hot bitumen on site

A sealing site has hot and flammable materials, moving plant and passing traffic. AfPA’s safety course for bituminous surfacing sites lists burns, boilovers, fire, fumes and reversing plant among the common hazards. So:

  • Keep children, pets and stock well away from the sprayer, the trucks and the fresh bitumen.
  • Stay out of the path of reversing tippers and rollers.
  • Follow the crew’s instructions and the binder’s safety data sheet.

What council and TMR jobs add

On departmental (TMR) jobs, the MRTS11 specification requires the following.

Item What MRTS11 requires on TMR jobs
Sprayer A current Queensland Sprayer Certificate issued by TMR; hand spraying only where the sprayer cannot reach
Seal design A designer with an AfPA or NTRO sprayed seal design qualification
Spray rate Within 5% of the adjusted design rate
Spray temperature 160 to 190°C for Class 170 bitumen
Weather No spraying in rain, when rain is likely before rolling is done, or in winds over 30 km/h
Pavement temperature Above 20°C for at least an hour before spraying Class 170 bitumen, unless the job’s annexure says otherwise
Covering the binder Stone spread within 10 minutes of spraying (5 minutes for polymer modified binders)
Rolling Multi-tyred rollers, at least 6 passes for bitumen binders
Records A spray sheet for every spray run
After sealing ‘Loose stones’ and ‘slippery’ signs and a temporary 40 km/h limit, where the posted limit is 60 km/h or less

Source: TMR MRTS11 (July 2025), clauses 9, 11, 12, 14 and 16 and Table 2. Emulsion work falls under MRTS12.

Councils and contractors can use our checklist for engaging a bitumen spraying subcontractor.

Spreading, rolling and sweeping the stone

Stone (aggregate) is spread straight onto the wet binder by a spreader, usually one stone thick, then rolled so the stones bed in and lie flat. Once the stone has bedded in, loose stone is swept off. The binder rate is designed around the traffic and the stone size.

  • Spreading: tippers with a tailgate hopper, or a self-propelled spreader, follow right behind the sprayer.
  • Rolling: multi-tyred rollers press the stone into the binder; steel-drum rollers are avoided because they can crush it.
  • Sweeping: loose stone is swept or vacuumed off without disturbing the bedded stone, because it can damage vehicles.

Chip seal, spray seal and ‘tar’: the same job

‘Chip seal’ is the New Zealand name for a sprayed seal (‘chip’ means the stone). Many people call it ‘tar’ (see ‘Is it tar?’ above).

How long the crew is on site

It depends on the area, truck access, whether a prime is needed first, and the weather. Ask for the expected time on site, and any separate visits, with your quote.

What to expect at your place on sealing day

Expect trucks, a bitumen (hydrocarbon) smell and a period when the sealed area is closed. Keep children and pets well away from the work, and avoid breathing the fumes, which a bitumen safety data sheet warns against. The crew’s instructions and the binder’s safety data sheet come first.

  • Trucks and noise: a sprayer, loaded tippers, a spreader, a roller and a broom work in sequence.
  • Smell: hot bitumen has a hydrocarbon odour; stay well back from the sprayer and avoid breathing the fumes.
  • Overspray: on TMR jobs the sprayer must keep bitumen off roadside furniture and clean off any that lands; at home, move cars, bikes, pot plants and hoses back from the edges.
  • Getting in and out: vehicles stay off until the stone is spread and the crew lets traffic on, so plan trips around the work.

When can cars, trucks and stock use a new spray seal?

Usually soon after rolling, but slowly and only when the crew says so, because the stone is still bedding in. Go slowly, with no tight turns or hard braking, and ask the crew when cars, loaded trucks and stock can each use it. This is not hot-mix asphalt, so waiting times quoted for new asphalt driveways do not apply.

What was laid What it is Why the waiting advice differs Where your timing comes from
Spray seal Bitumen sprayed and covered with rolled stone Traffic can go on almost as soon as the stone is spread, at strictly controlled speed, while the stone keeps bedding in The crew’s instructions for your job
Primerseal on a new base A first sprayed seal, built to carry traffic before the final surface It is a working surface, often for months, before the final seal or asphalt The crew, for your job
Hot-mix asphalt A premixed material made in a plant, laid hot and compacted It must cool before it can carry traffic without deforming; online asphalt times describe this The asphalt contractor

Source: Austroads AGPT Part 4K (2026), sections 3.2.2, 6.7 and 7.2.6; TMR TN186 (2019), section 1.1; TMR MRTS30 (March 2024), clause 8.4.

Cars and light vehicles

Drive slowly and straight where you can. Avoid turning the wheel while stopped, hard braking and tight turns at the house, shed and entrance, because turning and braking tyres pull stone from a new seal. Slow traffic helps settle the stone, while speed damages a fresh seal.

Loaded trucks, machinery, stock and yard traffic

Austroads notes that more heavy trucks in hot weather, such as at harvest or for stock transport, can affect a seal’s performance for up to two summers after it is laid. Traffic is a main input to the seal design, so when you ask for a quote, tell the crew about:

  • the trucks and machinery that will use the surface, and their loads
  • harvest, stock-truck or other seasonal peaks
  • stock crossings and laneways
  • whether the yard must keep working, so the job can be staged

Keep stock off the new seal until the crew says it is ready.

Hot days in the first weeks

In the first spell of hot weather, the binder in a new seal can soften and bleed up through the stone, leaving shiny, sticky patches. Avoid tight turns on hot afternoons and tell the crew about any sticky or shiny patches.

Rain soon after sealing

On TMR jobs, spraying does not go ahead in rain or when rain is likely before the stone is spread and rolled, and cold, damp conditions raise the risk of tyres stripping stone. Rain and the seasons are covered in best time of year to spray seal.

Aftercare in the first weeks

For the first weeks, drive slowly, avoid turning the wheels while stopped, keep fuel and oil off the surface and expect some loose stone. Soft or shiny binder can show on the first hot days and is worth telling the crew about. Spreading bare patches, or stone loss in the wheel paths, are worth a call.

  • Loose stone: expect some; even on TMR roads a small amount is allowed when a new seal reopens. Ask whether a follow-up sweep is part of the job.
  • Fuel and oil: keep spills off the surface, because repeated oil and diesel spills can break down bitumen-bound surfaces (Austroads notes it on asphalt).
  • Settling: the stones keep settling onto their flat side under traffic, mostly in the first year or two.
  • Warning signs: report spreading bare patches or stone loss early, because some problems can take months to show.

If you notice bare patches or stone loss, contact us.

Frequently asked questions

How do you chip and seal a road?

A chip seal is a spray seal, and a road is done the same way as a drive. The base is checked and swept, a new base is primed or primersealed, bitumen is sprayed, stone is spread straight onto it and rolled, and loose stone is swept off while traffic runs slowly. Road jobs also need traffic control. For private or shared roads, see sealing a private or shared road.

How do you spray seal a driveway?

You book a crew with a sprayer truck, a stone spreader and a roller. The drive is checked and swept, a new gravel base is primed or primersealed, then bitumen is sprayed, and stone is spread, rolled and swept. Truck access, turning areas and drainage need planning. For a long rural drive, see how we seal driveways and rural roads on the Sunshine Coast.

Is it easy to seal your own driveway?

Not with a spray seal. Bucket sealers (sealcoat) are typically coatings for existing, weathered asphalt, not a new surface. A spray seal needs bitumen (hot bitumen or an emulsion) from a sprayer truck, stone straight after it and rollers, on a site with burn and fire hazards, so it is work for a sealing crew. For a driveway, ask for an on-site quote.

How long does it take for bitumen to harden?

On a spray seal, slow traffic can usually go on almost as soon as the stone is spread, and the stones keep settling under traffic, mostly over the first year or two. Emulsions gain strength more slowly than hot bitumen, so traffic may wait longer, especially in cool weather. Your crew gives the timing for your job; see our bitumen spray sealing service.

How long before you can drive on new bitumen or ‘tar’?

On a new spray seal, traffic can usually go on soon after rolling, slowly and when the crew says so; check with the crew when cars, loaded trucks and stock can each use it. Online waiting times for new asphalt driveways are for hot-mix asphalt, which must cool first, so they do not apply. Ask for your reopening instructions when you contact us.

What does tarring a road involve?

‘Tarring’ is what many people call spray sealing: bitumen is sprayed onto a prepared base, covered with stone, rolled and swept. No tar is used; modern sprayed seals use bitumen refined from crude oil, and coal tar is no longer used for sprayed sealing. See bitumen vs tar for the difference.

Does bitumen smell?

Yes. Expect a bitumen (hydrocarbon) smell on sealing day. Keep children and pets well away from the work, avoid breathing the fumes, and follow your crew’s instructions and the binder’s safety data sheet. Our section on what to expect at your place on sealing day explains how to get ready before the crew arrives.

Talk to us about your job

Based in Cooroy, working across the Sunshine Coast, Noosa and Gympie, Brisbane north, Moreton Bay, the Fraser Coast, the Burnetts, Bundaberg, Toowoomba and the Western Downs. See our service areas. Monday to Friday, 6am to 6pm.

Sources

All checked 25 September 2026.

About Us

Established in 2005, Cuzkell Pty Ltd is a family-run business based in Cooroy, working across the Sunshine Coast, Noosa and Gympie. We also take on work in Brisbane north, Moreton Bay, the Fraser Coast, Bundaberg, the North and South Burnett, Toowoomba and the Western Downs. Call (07) 5447 6619 to check whether we can reach your site.
Contact Us

Office: 07 5447 6619

Anthony: 0427 890 222

Joel: 0428 896 333

ABN: 78 650 464 136

ACN: 650 464 136

Trading Hours
Mon - Fri             - 
Sat - Sun                              Closed
Copyright © 2025, Website design and hosting by Smart Local
© 2025 All Rights Reserved | Cuzkell Pty. Ltd